Karibu

Karibu kwa huduma za Logo Design, Poster & Flyer Design, Motion Graphics, Website & Blog Design, Video Promotion, Product Labels, Company Profiles na zaidi... WASILIANA NASI NA KARIBU SANA..!

Business Plan for Gold Processing Plant (Sehemu ya 2)

 
A BUSINESS PLAN FOR 6 VAT LEACHING PLANT

DATA (Assumed)

- Before doing design, you need some baseline data often from lab tests or pilot tests. For example

Volume & Tank Design

You need to design your vats so that 10 tonnes of ore fits in each.

Step A: Estimate the volume of ore in each vat (solid only)

- Ore density = 2.5 t/m³

- So 10 t of ore → volume = 10 / 2.5 = 4 m³

- But with 10% shrinkage / voids when wetted → effective volume required = 4 × 1.1 = 4.4 m³

So each vat must hold ~4.4 m³ of ore.

Step B: Vat geometry

Let’s pick a vat depth of 1.5 m (common in vat design)

- If depth = 1.5 m, then cross-sectional area needed = 4.4 / 1.5 = 2.93 m²

- Suppose we choose a square vat (for simplicity)—side length = √2.93 ≈ 1.71 m

- Or a circular vat: area = π * (r²) = 2.93 → r ≈ 0.965 m, diameter ≈ 1.93 m.

Step C: Solution freeboard & drainage

- Add 0.1 m solution height → total depth ~1.6 m

- Slope at 0.8% bottom improves drainage toward outlet.

- floor above bottom (~0.1–0.2 m) for filtering layer or supporting media

Scheduling & Throughput

With 72-hour retention:

- Cycle time = 3 days.

- You have 6 vats, so ideally every day one vat is loaded, one is leached, one drained, etc.

- Throughput per day = 60 t / 3 = 20 t/day

- Monthly (30 days) throughput = 20 × 30 = 600 t/month

Gold Recovery & Revenue Estimate

Using the assumption:

- Grade = 5 g/t

- Recovery = 85%

- Throughput per day = 20 t → gold content = 20 t × 5 g/t = 100 g

- Recovered = 100 g × 0.85 = 85 g/day

If gold sells at (assume) USD 60 per gram:

- Daily revenue = 85 × 60 = USD 5,100 

- Monthly revenue = 5,100 × 30 = USD 153,000

(This is ideal—ignores losses, operational costs, taxes, etc.)

Reagent & Operating Cost Estimation

- NaCN consumption = 1 kg/ton → 20 kg/day

- Lime, water, power, labor, maintenance, etc.

- NaCN cost at USD 5 / kg → 20 × 5 = USD 100/day

- Other reagents & utilities = USD 200/day

- Labor, maintenance, overhead = USD 300/day

Total OPEX = ~ USD 600/day

Profit before capex = 5,100 – 600 = USD 4,500/day

Capital Cost Estimation

Key cost items:

- Tanks (6 vats with liners, civil works)

- Pumps, piping, solution tanks

- Gold recovery system (carbon columns or zinc plant)

- Crushing unit

- Laboratory, building, site works

- Safety, spill control, waste collection

Let’s assume capital cost ~ USD 200,000

At that rate and profit, you recover capital in under 50 days (if ideal). In practice, scaling

inefficiencies, downtime, etc will lengthen payback.

Optimization & Sensitivity

- If recovery drops to 80% → revenue drops

- If cyanide cost increases → margins shrink

- If throughput fluctuates → smooth scheduling is needed

- Monitor pH, cyanide concentration daily, adjust loading, agitation (if used), aeration, etc.

Use response surface methodology (RSM) from lab tests to optimize cyanide concentration, pH,

particle size.

Risk & Mitigation

Risks include:

- Ore variability

- Channelling / non-uniform flow

- Cyanide losses / environmental damage

- Power interruption, equipment failure

Mitigations:

- Pilot test different zones of ore

- Use liner & monitoring sensors

- Tailings detoxification

- Backup power, maintenance plans