CASE STUDY
ESTABLISHING 6 VAT LEACHING TANKS FOR GOLD PROCESSING PLANT
Scaling up a gold VAT leaching operation into a small-scale plant with 6 leaching tanks requires translating lab/pilot test knowledge into a fully functional, compliant, and profitable gold recovery operation.
Below is a detailed breakdown of key steps with examples, specifically for someone starting their own gold VAT leaching plant.
1) Review Lab & Pilot Test Results
Objective: To Confirm that your ore is economically leachable using cyanide and determine optimal conditions.
DATA
Conduct laboratory leach tests (using 1–5 kg ore samples) to determine:
- Gold recovery % (e.g., 80–90%)
- Optimal particle size (e.g., -6 mm crushed)
- Leach time (e.g., 48–72 hours)
- Cyanide & lime dosage
- Ore behavior (oxidized or refractory)
RESULT (Assumed):
- Recovery: 88%
- Retention time: 72 hrs
- Cyanide: 0.5 kg/ton
- pH: Maintain at 10.5 (with lime)
- Crushed ore size: 80% passing 6 mm
2) Process Design
Objective: Design a system that replicates and scales up lab results.
Key Areas:
- Tank size: Decide based on daily ore throughput.
- Number of tanks: You chose 6 tanks.
- Tank material: Concrete (lined) or steel
- Flow design: Use batch or semi-continuous loading
RESULT
- Ore processed per batch: 10 tons per vat
- Each tank holds: 10 tons → 60 tons total
- Retention: 3 days per batch
- Process 20 tons/day (2 tanks loaded daily)
3) Infrastructure Setup
Objective: Build physical and utility infrastructure.
Site Requirements:
- Secure land (safe from flooding, near ore source)
- Water source (for mixing and washing)
- Power (for pumps, lighting, possibly crushing)
Structures to Build:
- 6 leaching tanks (1.5 m deep, 3 m diameter)
- Ore yard
- Crushing area
- Sluice or vibrating screen
- Solution tanks (pregnant & barren)
- Recovery room (carbon columns or zinc box)
4) Reagent Management
Objective: Ensure correct chemical usage and safety.
What You Need:
- Cyanide (NaCN)
- Hydrated lime (Ca(OH)₂) to maintain pH
- Safety storage containers (labelled)
- Spill kits and PPE
DATA
- For 10 tons ore:
- Cyanide: 5 kg
- Lime: 10–15 kg
- Mixed with water in a dosing tank and pumped into vats
5) Health, Safety & Environment (HSE)
Objective: Meet safety standards to avoid legal, environmental, or health issues.
What to Do:
- Train workers in cyanide handling
- Use PPE: gloves, goggles, boots, masks
- Construct bund walls around tanks to prevent spillage
- Build tailings pit for safe discharge
- Install emergency showers
6) Operational Planning
Objective: Establish daily routines, staffing, and processes.
Manpower:
- 1 Plant Supervisor
- 3–5 Operators (feeding, mixing, cleaning)
- 1 Chemist or Lab Technician (even basic testing)
- 1 Security Guard
Operation Steps:
1. Crush ore to -6 mm
2. Load 10 tons into each vat
3. Add lime and cyanide solution
4. Wait 3 days (leaching)
5. Drain pregnant solution
6. Recover gold (carbon or zinc)
7. Wash and discharge tailings
7) Monitoring & Optimization
Objective: Adjust processes to improve performance over time.
Key Monitoring Parameters:
- pH (Target: 10.5–11)
- Cyanide concentration (0.05–0.1%)
- Gold in solution (check every 24 hrs)
- Recovery rate
DATA
After first cycle:
- Gold recovery: 75%
- Adjust retention to 84 hours
- Use finer crush to -4 mm next batch
8) Recovery Method
- Carbon in Column (CIC): Good for small operations
- Zinc Precipitation: If you use Merrill-Crowe type system
9) Gold Smelting:
After recovery, smelt gold into dore bars using:
- Smelting furnace
- Flux (borax, soda ash)
- Crucibles
Estimated Budget
NOTE:
- Work with a metallurgist or experienced consultant at the start
- Keep detailed records
- Recycle barren solution where possible
- Consider licensing and environmental permits with local authorities (Tanzania: TMAA, NEMC, etc.)
PLANT OPERATION AND ESTIMATED BUDGET
Process Flow Diagram
Crushing → Screening → Vat Leaching → Solution Collection → Gold Recovery → Smelting → Dore Bars
Preparation
1. Ore Receiving Yard
2. Crushing Unit → Reduce ore to -6 mm
3. Screening (optional)→ Remove oversize
4. Loading into Vats (6 Tanks)
5. Add Lime & Cyanide Solution
6. Leaching (72 hrs per vat)
7. Collect Pregnant Solution
8. Gold Recovery (Carbon or Zinc)
9. Smelting → Dore Bars
10. Tailings Disposal
Business Plan
❖ Executive Summary
- Establish a 6-Vat gold leaching plant in site
- Target: 60 tons crushed ore per cycle (10 tons per tank)
- Recovery method: Vat leaching + Carbon
❖ Business Objectives
- Recover gold from oxidized ore at small scale
- Operate legally with environmental compliance
- Scale production within 2 years
❖ Market Opportunity
- Availability of artisanal ore
- Growing demand for gold in local & international markets
❖ Technical Plan
- Technology: Manual crushing, vat leaching, basic lab
- Inputs: Crushed ore, lime, cyanide, water, carbon
- Skilled labor: Metallurgist (consultant), operators, technician
❖ Financial Plan (Assumed)
❖ Revenue Forecast
- Gold grade: 5 g/t
- Recovery: 80%
- Gold per batch: ~24 grams
- Monthly production: ~240g
- Revenue (240g @ TZS 160,000/g): TZS 38.4M
THANK YOU
